There are now strict timelines for the Engineer to reach a determination. If they fail to act within the specified timeframe, it is often deemed a rejection, allowing the parties to move to the next stage of dispute resolution. 3. Reciprocity of Obligations
The "DAB" (Dispute Adjudication Board) has evolved into the .
This increased detail creates a higher administrative burden. Failure to follow these specific workflows can lead to a loss of rights or claims. 2. Enhanced Role of the Engineer fidic 2017 a practical legal guide pdf
The most immediate change in the 2017 Suite is the length. The contracts are significantly longer, primarily due to "step-by-step" procedures designed to reduce ambiguity.
Several clauses now include "deemed" outcomes if a party fails to respond. Knowing these "silent" triggers is critical to protecting your legal position. Conclusion There are now strict timelines for the Engineer
Under Sub-Clause 20.2.1, a party must give notice of a claim within 28 days of becoming aware of the event.
FIDIC now mandates a standing board (appointed at the start of the project) rather than an ad hoc board. it is often deemed a rejection
Due to the administrative intensity, you need a dedicated contract management team. You cannot manage a 2017 contract "off the corner of your desk."